مشاريع الخدمات الصناعية لـ تيكوركس
# | الاسم | العميل | معلومات الاشخاص | السنة | الحالة | تفاصيل | الملف |
---|---|---|---|---|---|---|---|
6 | Upgrading of 115Kv Protection at SEC Jisha & Idwa Substations | Power Flow Contracting | Upgrading of 115Kv Protection at SEC Jisha & Idwa Substations | 2015 | Completed | - Upgrading and Testing of SCADA System - Installation of 115Kv Protection Panels - Testing and Commissioning of 115Kv Surge Arrestor and accessories. | فتح الملف |
7 | Installation of Two (2) MetalClad Switchgear 13.8kV 1250V in SEC SANG S/S | Saudi Edrak Contracting Co. Ltd. | Saudi Edrak Contracting Co. Ltd. | 2015 | Completed | - Testing of O/C Relays (Mfr: ABB, Model: REF615) - Testing of Power Meter (Mfr: Integra, Model: 1530) - Testing of Trasducers, TRIAD2 - Mark-up Drawings of Two Metalclad Switchgear 13.8kV 1250A in SANG S/S | فتح الملف |
8 | Upgrading of Busbar Protection and Transformer Protection at SEC Faras and Shedgum Power Plant | Power Flow Contracting | Power Flow Contracting | 2016 | Completed | - Upgrading and Testing of SCADA System - Installation 380Kv Busbar Protection and 380/230Kv Transformer Protection panels. | فتح الملف |
9 | Resolve the Frequent Electrical Interruptions at Station 25 in Al-Ahsa | Saudi Irrigation Organization | Saudi Irrigation Organization | 2017 | Completed | - Re-engineering and design the station electrical scheme. - Re-habilitation of existing circuit breakers | فتح الملف |
10 | Major PM of Four (4) Main 13.8 KV/230KV 133MVA Generators Transformers at Shedgum Power Plant | KAFOU Technical Services | KAFOU Technical Services | 2018 | Completed | - Take oil samples and perform DGA and oil test as per ASTM standard. - Test and calibrate temperature indicators, Bucholz relays, sudden pressure relays, pressure relief device etc and replace if defective. - Inspect Conservator level gauges for Main tank and OLTC. Inspect On-Load and Off –Load tap changer parts, test tap changer by manual and electrical operation, and replace any defective parts. Test OLTC oil for healthiness. Replace oil if required. - Perform the electrical test of the transformer for Insulation resistance and PI of HV and LV winding, Excitation current test, Resistance measurement of HV and LV winding , Turns ratio test at all tap positions, Insulation power factor test for transformer windings and associated bushings. Grounding Transformer, Neutral grounding Resistors, Reactors. | فتح الملف |
11 | Replacement of Three Transformers at Saudi Irrigation Organization in Al-Ahsa (Northern Area) | Saudi Irrigation Organization | Saudi Irrigation Organization | 2018 | Completed | - Dismantling of existing three (3) transformers - Erection & installation of three (3) new transformers (1000KVA, 13.8/400-270) - Installation of three (3) Manual Transfer Switch - Laying and termination of 630MM2 cables - Testing & Commissioning. | فتح الملف |
12 | Replacement of Three Transformers at Saudi Irrigation Organization in Al-Ahsa (Southern Area) | Saudi Irrigation Organization | Saudi Irrigation Organization | 2018 | Completed | - Dismantling of existing three (3) transformers - Erection & installation of three (3) new transformers (1000KVA, 13.8/400-270) - Installation of three (3) Manual Transfer Switch - Laying and termination of 630MM2 cables - Testing & Commissioning. | فتح الملف |
13 | Installation, Testing & Commissioning of Eight (4) Line Protection Panels for Mahasen - Hajer 115kV Line | FAST LINX Trading & Industrial Supplies | FAST LINX Trading & Industrial Supplies | 2018 | Completed | - Complete Engineering & Design for new eight (4) Line protection panels. - Dismantling of existing eight (4) protection panels at four substations. - Erection & installation of eight (4) new protection panels and two (2) communication converter panels (wall-mounted) - Laying & termination of cables from new installed panels to CTs, SCADA RTU, SOE, Ann., DFR, and DC panels. - Testing & Commissioning (complete functional tests) of installed equipment | فتح الملف |
14 | Testing of Four (4) Transformers (13/20 MVA, 33/13.SKV) in Central Area, Saudi Arabia | "TAQQAT A member of Abdullah Fouad Group" | TAQQAT A member of Abdullah Fouad Group | 2018 | Completed | To perform onsite testing of 4 nos. 13/20 MVA, 33/13.SKV Transformers (2 in RIYADH PP4, 1 in ALKHARJ, and 1 in ALQASSIM), that include Sweep Frequency Response Analysis (Finger print test), Calibration of Transformer winding & oil temperature gauges, Excitation Current Test, and Record all the Test report of the Transformer. | فتح الملف |
15 | Supplying, Instalation & Testing and commissioning of Four (4) Water Mixer at Zone 3. | Saudi Irrigation Organization | Saudi Irrigation Organization | 2019 | Completed | Supplying, Instalation & Testing and commissioning of Four (4) IEC Water Mixer (20 HP) at Zone 3 Water Tank. | فتح الملف |
16 | 125MVA Power XFMR Oil evacuation, Filling & Filtration Activities at RAS QURRIYAH GCC Substation. | Cegelec Saudi Co. | Cegelec Saudi Co. | 2019 | Completed | 125MVA Power XFMR Oil evacuation, Filling & Filtration Activities at RAS QURRIYAH GCC Substation. | فتح الملف |
17 | Vacuuming Process of Unit Transformer at Qurriyah PP. | JAL International | JAL International | 2019 | Completed | Preforming Vacuuming Process of Unit Transformer at Qurriyah PP. | فتح الملف |
18 | Corrective maintenance (CM), perventive maintenance (PM) and system analyzing of MV and LV equipment for HIDA at Al Amariyah Station | Saudi Irrigation Organization | Saudi Irrigation Organization | 2019 | Completed | Breaker & cutout swithes test procedure: - Perform General inspection. - Open / close operation response. - Contact resistance test. - Insulation resistance test. - Timing test for MV barker. Relay Test Procedures: - Visual check. - Isolation Check. - Check the existing relay setting and compare it with setting sheet and then change what ever required. - Pick up Test as per the setting. - Timing test. - Trip Test. Transformer Test Proucedures: - Oil filtration and oil changing. - Visual check. - Cleaning. - Winding insulation test. - Terminals check. | فتح الملف |
19 | Supplying, Insalling & Testing and Commissioning of Two (2) GEFRAN Motor VFDs At Al Omran Sation. | Saudi Irrigation Organization | Saudi Irrigation Organization | 2019 | Completed | Supplying, Insalling & Testing and Commissioning of Two (2) GEFRAN Motor VFDs (350KW-380V-60HZ) At Al Uyon Sation. | فتح الملف |
20 | Supplying, Insalling & Testing and Commissioning of Three (3) GEFRAN Motor VFDs with inclosures At Al water Treatment Sation. | Saudi Irrigation Organization | Saudi Irrigation Organization | 2019 | Completed | Supplying, Insalling & Testing and Commissioning of Three (3) GEFRAN Motor VFDs with inclosures (15KW-380V-60HZ) At Al water Treatment Sation (Main Office) | فتح الملف |
21 | Perventive Maintenance (PM) of 480V of 32 circuit breakers. | KAFOU Technical Services | KAFOU Technical Services | 2019 | Completed | Breaker & cutout swithes test procedure: - Perform General inspection. - Open / close operation response. - Contact resistance test. - Insulation resistance test. - Timing test for MV barker. | فتح الملف |
22 | Dismantelling of Stainless-steel oil tank, supplying, istalling & connecting new oil tank in Al Hasa National Guard King Abdulaziz Hospital. | Al Hasa National Guard King Abdulaziz Hospital. | Al Hasa National Guard King Abdulaziz Hospital. | 2019 | Completed | Oil Tank Dismantelling: - Removing The old oil tank. - Cleaning of cach base of the tank. Oil Tank Supplying, Installing And connecting: - Supplying a new Stainless-steel oil tank. - Intallatttion of new one. - Connecting new one by doing all pipping work. | فتح الملف |
23 | Corrective maintenance (CM), perventive maintenance (PM) and system analyzing of MV and LV equipment for HIDA at Domat Al jandal for 18 wells & 5 main station. | Saudi Irrigation Organization | Saudi Irrigation Organization | 2019 | Completed | Breaker & cutout swithes test procedure: - Perform General inspection. - Open / close operation response. - Contact resistance test. - Insulation resistance test. - Timing test for MV barker. Relay Test Procedures: - Visual check. - Isolation Check. - Check the existing relay setting and compare it with setting sheet and then change what ever required. - Pick up Test as per the setting. - Timing test. - Trip Test. Transformer Test Proucedures: - Visual check. - Cleaning. - Winding insulation test. - Terminals check. | فتح الملف |
24 | Perventive Maintenance (PM) and system analyzing of MV and LV equipment for HIDA at Al Uyon Pump station, Omran Pump Station, Kilo1,3&4 and HIDA main office main supply station. | Saudi Irrigation Organization | Saudi Irrigation Organization | 2019 | Completed | - PM of 3 circuit breakers 13.8kv/630Amp. - PM of 4 circuit breakers 4000Amp. - PM of one circuit breaker 875Amp. - PM and testing of 5 transformers 13.8kv/480v. - PM of 5 circuit breakers 1250Amp. - PM of 4 circuit breakers 800Amp. - PM of 10 circuit breakers 2000Amp. - PM of one circuit breaker 16000Amp. - PM of 2 circuit breakers 1000Amp. - Functional test of 5 ATS. - PM of 4 cirRing Main Unit (RMU). - PM of 2 Protection system. | فتح الملف |
25 | MV/LV CBs 97 panels & RMUs Testing Scope at KSAU-HS-ER | JASH TECHNICAL SERVICES CO.LTD | JASH TECHNICAL SERVICES CO.LTD | 2019 | Completed | Breaker test procedure: - Perform General inspection. - Open / close operation response. - Contact resistance test. - Insulation resistance test. - Timing test for MV barker. Relay Test Procedures: - Visual check. - Isolation Check. - Check the existing relay setting and compare it with setting sheet and then change what ever required. - Pick up Test as per the setting. - Timing test. - Trip Test. | فتح الملف |
26 | Installation, Testing & Commissioning of Eight (4) Line Protection Panels Uthmaiyah PP – RWPS # 4 115kV Line | FAST LINX Trading & Industrial Supplies | FAST LINX Trading & Industrial Supplies | 2019 | Completed | - Complete Engineering & Design for new eight (4) Line protection panels. - Dismantling of existing eight (4) protection panels at four substations. - Erection & installation of eight (4) new protection panels and two (2) communication converter panels (wall-mounted) - Laying & termination of cables from new installed panels to CTs, SCADA RTU, SOE, Ann., DFR, and DC panels. - Testing & Commissioning. | فتح الملف |
27 | Corrective maintenance & system analyzing of LV equipment at Station#10 | Saudi Irrigation Organization | Saudi Irrigation Organization | 2019 | Completed | - System analyzing of LV system. - Preparing new drawings of the exsisting scheme. - LV bus maintainance & electrical testing. - Redesigning the scheme. - Correcting the ATS scheme of incomers & bus-tie. - Correcting the ATS scheme of stand-by generator and LV system. | فتح الملف |
28 | Corrective maintenance of LV equipment, trouble shooting for automatic transfer scheme for main source and reolace MV bus tie breaker at Station#6 | Saudi Irrigation Organization | Saudi Irrigation Organization | 2019 | Completed | - Trouble shooting of closing and opening circuit for LV bus coupler “Q2” & incomer#1 “Q1”. - Supplying one LV BKR. - Replacing of LV bus coupler “Q2” with new one. - Testing and maintaining of LV bus coupler “Q2”, incomer#1 “Q1” & incomer#2 “Q3”. | فتح الملف |
29 | Re-designing & upgrading of LV CBs Distrbution Panels, Installation Scope For Gasolin Station at HIDA Main Office | Saudi Irrigation Organization | Saudi Irrigation Organization | 2019 | Completed | - Dismantling existing old Panels. - Shifting old panels to customer store. - Relocating & Instalation of new condotes & new panels. - New wires pulling. - Terminations. - Relocating of Automation system. | فتح الملف |
30 | Repair work for the burned Air Circuit Breaker in MCC-2D at SEC Qurayyah Power Plant | KAFOU Technical Services | KAFOU Technical Services | 2019 | Completed | - Remove the existing air circuit breaker (01) and replace with brand new air circuit breaker (with overcurrent relay) from SEC approved OEM’s. - All components in the Incomer ACB’s cubicle, Incomer ACB’s Protection cubical, Turning Oil Pump ACB’s Cubicle, and Air Extraction Vacuum Pump ACB’s cubical shall be replaced by brand new components. - Minor T&I shall be performed on all air circuit breakers except the new replaced air circuit breaker (total 5 breakers). - Minor T&I shall be performed on all MCCB. | فتح الملف |
31 | Power XFMRs Corrective Maintenance (CM) Activities at SEC Faras Power Plant | KAFOU Technical Services | KAFOU Technical Services | 2019 | Completed | - Pressure relief devices and OLTC main buchloz relay not operate the lock out relay for GSU # 16 - Mechanical devices not operate the lock out relay for GSU # 17 - Standing alarm in hydrant device for GSU # 17 | فتح الملف |
32 | Supply, installation and commissioning of protection and control panel at Omran S/S | Saudi Irrigation Organization | Saudi Irrigation Organization | 2020 | Completed | Supply, installation and commissioning of protection and control panel at Omran S/S including excavation, supply and lating of power and control cables, errection of cable trays and terminations as per approved standards. | فتح الملف |
33 | MV XFMRs Maintenance at National Industrial Training Institute (NITI) | Ezdan | Ezdan | 2020 | Completed | Carrying out major PM & oil filtration for MV transformer in National Industrial Training Institute (NITI). | فتح الملف |
34 | Supply and Installation Solar Lighting System at HIDA Envoirmental Station | Saudi Irrigation Organization | Saudi Irrigation Organization | 2020 | Completed | Supplying, Installing, Tsting & Commissioning and energizing Sloar Lights for Invoirmental Station. | فتح الملف |
35 | Modification of station’s pumps control system & VFDs system at HIDA – Al Omran Station – Sector No. 9 | Saudi Irrigation Organization | Saudi Irrigation Organization | 2020 | Completed | Modifying the control system of the pumps by Supplying, Installing, Tsting & Commissioning and energizing LCP, MCCP, Junction box, control cables, power cables, installing cable tray, making cable trunches & manhole. | فتح الملف |
36 | MV Substation cables Testing at Alamer Mall North | Abdullah Ali Alamer & Brother Trading Co. | Abdullah Ali Alamer & Brother Trading Co. | 2020 | Completed | Performing electrical Testing for MV cables for seven (7) MV XFMRs & seven (7) RMU | فتح الملف |
37 | Rectifying HV chamber oil leakage problem for 40MVA Shunt reactor #2 in SEC – Dammam Housing 380/115/13.8KV BSP | TAQQAT Global Co. | TAQQAT Global Co. | 2020 | Completed | - HV chamber oil draining retification of oil leakage near the pressure release device coupling plunge of shunt# 2 & hv chamber oil filling & oil quality after oil (DGA & oil quality after oil filteration before refilling hv chamber) of shunt reactor # 2 (S.#20154299TRC025-002) (MAKE: HHI, KOREA) (40MVAR) in Dammam Housing 380/115/13.8KV BSP. | فتح الملف |
38 | Major Electrical System Modification at HIDA Main office water desalination plant | Saudi Irrigation Organization | Saudi Irrigation Organization | 2020 | Completed | - Supplying, Installing, Tsting & Commissioning and energizing Three (3) 15KW VFDs with its control panels. - Supplying, Installing, Tsting & Commissioning and energizing SCADA System & PLC System and connecting them to control center. - Supplying, Installing, Tsting & Commissioning and energizing (MCC remote I/O and HMI) for water Pumps. - Supplying, Installing, Tsting & Commissioning and energizing (Infield remote I/O). - Supplying, Installing, Tsting & Commissioning and energizing water tanks (LEVEL TRANSMITTERs). - Supplying, Installing, Tsting & Commissioning and energizing the pumps control operation system by configuring the communication/control commands protocol. Activating differential & integral control system for the VFDs. - Supplying, Installing, Tsting & Commissioning and energizing Motorized Valves and connecting their control to the control system. | فتح الملف |
39 | Corrective maintenance (CM) of MV and LV equipment for HIDA at Riyadh Main Station | Saudi Irrigation Organization | Saudi Irrigation Organization | 2020 | Completed | Breaker: - Repairing Racking-In & Racking-Out problem of Main CB (SGA-101) for Transformer No. (TR101). - Repairing Opening & Closing problem of Ground switch for transformer (TR 102). - Repairing Opening & Closing problem of Disconnect switch for transformer (TR 101). - Insulation resistance test. - Timing test for MV barker. - Performing PM for (44) 380V CBs. - Performing PM for (7) main distribution Panels Relays. Battary & Battary Charger: - Performing PM for DC system including its protection. Pump: - Repairing Pump # (G-101) terminals. Transformer: - Performing electrical tests for 5MVA Aramco Transformer. - Repairing & rewinding Three(3) cooling fans for XFMR# (TR 101). - Repairing & rewinding cooling fans for XFMR# (TR 121 & TR 102). - Performing PM for Two(2) grounding transformers. - Performing PM for Three(3) 4.16KV Disconnect Isolators. Potintial Transformers: - Performing PM & Testing of PTs | فتح الملف |
40 | 125MVA Shunt Reactor Dismantilling Activities at RAS QURRIYAH GCC Substation. | Cegelec Saudi Co. | Cegelec Saudi Co. | 2020 | Completed | - Oil draining of 125MVA Shunt Reactor. - Assesting in 125MVA Shunt Reactor Dismantilling. | فتح الملف |
41 | Supplying, Installation LED screen 2.88m x 2.88m, pixcel pitch 6 outdoor with its steel structure for Led Secreen. | Abdullah Saeed Al Ghamdi (ASGE) Group | Abdullah Saeed Al Ghamdi (ASGE) Group | 2020 | Completed | - Supplying, Instalation steel structure for Led Secreen. - Supplying, Instalation LED screen 2.88m x 2.88m, pixcel pitch 6 outdoor. | فتح الملف |
42 | Supplying, Installation & Testing and commissioning of Power Factor System at Al Omran Station. | Saudi Irrigation Organization | Saudi Irrigation Organization | 2020 | Completed | Supplying, Instalation & Testing and commissioning of Power Factor System at Al Omran Station. | فتح الملف |
43 | Checking and re-filling of SF6 Gas for ABB type CTC-F RMU. | Civil Works Co. | Civil Works Co. | 2020 | Completed | Checking and re-filling of SF6 Gas for ABB type CTC-F RMU. | فتح الملف |
44 | توريد كيبل كهربائي CABLE CU/XLPE/PVC 1KV 1C*300 MM2) كيبل كهرباء | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | توريد كيبل كهربائي CABLE CU/XLPE/PVC 1KV 1C*300 MM2) كيبل كهرباء | فتح الملف |
45 | صيانة اللوح المغذية لمخارج المزارعين (SCADA Panel) | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | صيانة اللوح المغذية لمخارج المزارعين (SCADA Panel) | فتح الملف |
46 | الصيانة التصحيحية والوقائية للمنظومة الكهربائية بقطاع 6 وقطاع 9 | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | الصيانة التصحيحية والوقائية للمنظومة الكهربائية بقطاع 6 وقطاع 9 | فتح الملف |
47 | صيانة تصحيحية ووقائية على المحولات والقواطع الكهربائية بفروع المؤسسة بالرياض والجارودية والأفلاج | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | صيانة تصحيحية ووقائية على المحولات والقواطع الكهربائية بفروع المؤسسة بالرياض والجارودية والأفلاج | فتح الملف |
48 | توريد صمامات لزوم قطاعات فرع الأحساء | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | توريد صمامات لزوم قطاعات فرع الأحساء | فتح الملف |
49 | ربط 3 مضخات إلى خزان التبريد بماسورة الإمداد الرئيسية بفرع المؤسسة العامة للري بمحافظة الأفلاج | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | ربط 3 مضخات إلى خزان التبريد بماسورة الإمداد الرئيسية بفرع المؤسسة العامة للري بمحافظة الأفلاج | فتح الملف |
50 | توريد وتركيب واستبدال مرشحات الهواء الحديدية للخلاطات (ايطاليا) | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | توريد وتركيب واستبدال مرشحات الهواء الحديدية للخلاطات (ايطاليا) | فتح الملف |
51 | تركيب وتشغيل منظومة كهربائية وميكانيكية لخزان التبريد لفرع المؤسسة العامة للري بمحافظة الأفلاج | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | تركيب وتشغيل منظومة كهربائية وميكانيكية لخزان التبريد لفرع المؤسسة العامة للري بمحافظة الأفلاج | فتح الملف |
52 | نقل شاشات التحكم (HMI) في كيلو 7 من غرفة التحكم الحالية إلى غرفة أخرى | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | نقل شاشات التحكم (HMI) في كيلو 7 من غرفة التحكم الحالية إلى غرفة أخرى | فتح الملف |
53 | صيانة المنظومة الكهربائية وفحص المحولات في المؤسسة العامة للري وفروعها | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | صيانة المنظومة الكهربائية وفحص المحولات في المؤسسة العامة للري وفروعها | فتح الملف |
54 | توريد وتركيب وتشغيل مخارج صمامات مزارعين مطورة لمكتب الحارة | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | توريد وتركيب وتشغيل مخارج صمامات مزارعين مطورة لمكتب الحارة | فتح الملف |
55 | إزالة مغير السرعة القديم مع كابلات الغذية الكربائية والتحكم وتوريد وتركيب واختبار متحكم السرعة للضخة (VFD) حسب المواصفات التالية: 75kw - 90kw (102-122 hp) 380/480V Gefran, Italy | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | إزالة مغير السرعة القديم مع كابلات الغذية الكربائية والتحكم وتوريد وتركيب واختبار متحكم السرعة للضخة (VFD) حسب المواصفات التالية: 75kw - 90kw (102-122 hp) 380/480V Gefran, Italy | فتح الملف |
56 | توريد جهاز قارئ تدفق المياه مزودة بجهاز القراءة الأساسي وحساس قراءة التدفق | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | توريد جهاز قارئ تدفق المياه مزودة بجهاز القراءة الأساسي وحساس قراءة التدفق | فتح الملف |
57 | توريد وتركيب لوحة تشغيل وتحكم وحماية كهربائية (مجهزة بطرفيات للتحكم عن بعد SCADA) مع ما يلزم من حفر خنادق وتوريد وتمديد كوابل تغذية وتحكم | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | توريد وتركيب لوحة تشغيل وتحكم وحماية كهربائية (مجهزة بطرفيات للتحكم عن بعد SCADA) مع ما يلزم من حفر خنادق وتوريد وتمديد كوابل تغذية وتحكم | فتح الملف |
58 | تضمين مضخة بئر التغذية الرئيسي (28 حصان) في منظومة التحكم الآلي وبطها بأجهزة قياس مستوى الماء في الخزان الرئيسي مع ما يلزم من أجهزة ومعدات | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | تضمين مضخة بئر التغذية الرئيسي (28 حصان) في منظومة التحكم الآلي وبطها بأجهزة قياس مستوى الماء في الخزان الرئيسي مع ما يلزم من أجهزة ومعدات | فتح الملف |
59 | Replacement of Old Breaker Mechanism with Installation of new Breaker in Meredian and other SEC stations in Dammam & Khobar | Branch Al- ataa Al-shamel General Contracting Company | Branch Al- ataa Al-shamel General Contracting Company | 2021 | Completed | Replacement of Old Breaker Mechanism with Installation of new Breaker in Meredian and other SEC stations in Dammam & Khobar | فتح الملف |
60 | Installation, Connection and Testing of Annuciator Panel at SEC Station, Jubail SS | American Techno Controls Co. | American Techno Controls Co. | 2021 | Completed | Installation, Connection and Testing of Annuciator Panel at SEC Station, Jubail SS | فتح الملف |
61 | Construction of 380KV D/C OHTLs for interconnection of Marjan 380KV BSP - Portion 1 | LARSEN & TOUBRO SAUDI ARABIA LLC | LARSEN & TOUBRO SAUDI ARABIA LLC | 2021 | Completed | 1- Shifting of Conductor, OPGW, Insulators and associated hardware, Spacer Damper to site, Insulator Hanging and Pilot wire Paying out for conductor 6-Phase. 2- Conductor Pulling (quad bundle) 6 Phase 3- Conductor Sagging, Conductor clipping, jumper and spacer Installation. 4- Roller Hanging and Pilot wire Paying out for OPGW 2 Ckt. 5- OPGW Pulling (Twin bundle) 2 Ckt, Lead Down, Sagging, Clipping | فتح الملف |
62 | SCC - calibration of energy meters | Saudi Cement | Saudi Cement | 2021 | Completed | Calibration of energy meters QYT=115 | فتح الملف |
63 | SCC - PM & Repair Battery Chagers Panel 17 | Saudi Cement | Saudi Cement | 2021 | Completed | PM & Repair Battery Chagers & Battery Bank QYT=17 | فتح الملف |
64 | Calibration of therty (30) energy meters in SEC Qurayyah PP | KAFOU Technical Services | KAFOU Technical Services | 2021 | Completed | Calibration of therty (30) Nexus-1250 energy meters in SEC Qurayyah PP | فتح الملف |
65 | Repair of oil leak for 6.9/2.08 kV 3250 KVA isolation transformer in JGP | Tihama Power Generation Company Ltd. | Tihama Power Generation Company Ltd. | 2021 | Completed | 1- Isolate transformer and disconnect HV terminals. 2- Drain oil to appropriate level. 3- Open HV side bushings. 4- Repair of oil leak by replacement of Gasket. 5- Toping up transformer’s oil level. 6- Oil filtration. 7- Perform BDV oil test. 8- Take oil samples for DGA test before and after oil filtration. 9- Submit technical report. | فتح الملف |
66 | PM for 132/13.8KV 90/110 MVA transformer in ARAR PP | KAFOU Technical Services | KAFOU Technical Services | 2021 | Completed | PM for 132/13.8KV 90/110 MVA transformer in ARAR PP | فتح الملف |
67 | Major PM & cold wash for T758 266MVA Transformer at SEC FARAS Power Plant | KAFOU Technical Services | KAFOU Technical Services | 2021 | Completed | Major PM of One (01) 266 MVA 230KV / 13.8KV transformer at FARAS PP and Oil filtration. | فتح الملف |
68 | Maintenance and Repair of two (02) MCC 480V CBs at Juaymah GP | Tihama Power Generation Company Ltd. | Tihama Power Generation Company Ltd. | 2021 | Completed | 1. Perform complete visual inspection and cleaning for MCC panel and associated 480V circuit breakers. 2. Perform necessary repair and maintenance for the affected two (02) 480V circuit breakers and their connection to busbar. 3. Perform overall insulation test for breakers and their associated connection to busbar. 4. Perform contact resistance test for breakers to ensure their integrity. 5. Addition of busbar resleeving for all phases related to affected breakers. 6. Busbar tightness as per OEM torque level (70-100 NM mostly) related busbar legs connected to the two affected breakers. | فتح الملف |
69 | INSTALLATION & REPLACEMENT OF MAJOR EQUIPMENTS AT 69kV AIR INSULATED BUS AT MERIDIEN SUBSTATION | Abdullah Fouad Co. | Abdullah Fouad Co. | 2021 | Completed | - To dismantle existing material, packing, handover to the main contractor. - Visual inspection of received material, site testing, installations, functions check, electrical connections. - Fitting, fabrication, alignment, ensure proper operational checks. - Mark up drawing with final dimensions to be prepared on IFC drawing as hand sketching only. - General routine tests only applicable (contact resistance, insulation test MEGGER, local/Auto operational checks, interlock checks, functional checks). | فتح الملف |
70 | Supply and installation of water ball valves | Saudi Irrigation Organization | Saudi Irrigation Organization | 2021 | Completed | Supply and installation of water ball valves in eastern province. | فتح الملف |
71 | Major PM of BOP transformer # 1 & 2 at Ghazlan PP , WO # 2202237418 | KAFOU Technical Services | KAFOU Technical Services | 2021 | Completed | 1. Perform visual inspection of any oil leakage of the transformer and clean as necessary. 2. Clean transformer body and radiators using proper cleaning materials and equipment. Wash radiator Banks thoroughly to clean dirt/dust. Perform PM of fan motors and oil pumps, if applicable. 3. Test and calibrate temperature indicators, Buchholz relays, sudden pressure relays, pressure relief device etc and replace if defective. 4. Inspect Conservator level gauges for Main tank and OLTC. Inspect Main tank Conservator rubber bag condition for healthiness. Repair/replace rubber bag if required and Top up Conservator oil levels if required. 5. Inspect/test tap changer by manual and electrical operation. 6. Touch up painting as necessary 7. Provide all necessary test equipment and perform the following Test of the transformer: • Insulation resistance and PI of HV and LV winding • Resistance measurement of HV and LV winding • Turns ratio test at all tap positions. | فتح الملف |
72 | Replacement of Faulty Transformer at SEC-Shedgum Power Plant | KAFOU Technical Services | KAFOU Technical Services | 2021 | Completed | 1. Disconnection the faulty transformer and remove from the foundation by skidding lifting tools Unit 15 Step- Up TFMR, T605 at Shedgum P/P. 2. Faulty Transformer to be shifted to nearby area. 3. Disassembling of the new transformer, shift it to place of faulty transformer. (KTS will provide lifting equipment only). 4. Reassembling of the spare TFMR to replace T605 TFMR at Shedgum P/P. (KTS will provide lifting equipment only). 5. Evacuating and Oil Filling TFMR. 6. To perform XFMR oil filtration 7. To Perform One Time Standard DGA and Quality Lab Test. 8. Perform Electrical Test (Insulation Resistance, Winding PF, Bushing PF, TTR, Winding Resistance). 9. Perform functional checks for mechanical protection devices. 10. Connect HV, LV, to the system. 11. Trace, label & Connect the control and auxiliary cables. | فتح الملف |
73 | Calibration of energy meters in SEC stations | GCC lab Calibration Services Co | GCC lab Calibration Services Co | 2021 | Completed | Calibration of more than 250 energy meters in SEC stations in eartern brovance as per SEC standards. | فتح الملف |
74 | Oil drainage, excavation, filling & filtering process for 125MVA shunt reactor ar RAQ substation. | Cegelec Saudi Co. | Cegelec Saudi Co. | 2021 | Completed | Oil drainage, excavation, filling & filtering process for 125MVA shunt reactor ar RAQ substation. | فتح الملف |
75 | Installation, testing and commisioing of DC motor at Meridian Substation in Khobar | American Techno Controls Co. | American Techno Controls Co. | 2021 | Completed | Installation, testing and commisioing of DC motor in SF6 GCB mechanism at Meridian Substation in Khobar | فتح الملف |
76 | MV cable termination for 2 MVA transformer @ Wisa area – National Water Company | Civil Works Co. | Civil Works Co. | 2021 | Completed | MV cable termination and testing for 2 MVA transformer @ Wisa area – National Water Company | فتح الملف |
77 | Modification and testing of LV generators | Shelf Drilling Co. | Shelf Drilling Co. | 2021 | Completed | - Installation of space heaters for three generators at yard’s workshop - Testing of four generators - Testing of three DC motors | فتح الملف |
78 | Testing and commissioning of LV panels at Jubail SWCC | ALMASSA | ALMASSA | 2021 | Completed | Testing and commissioning of LV panels for three stations at Jubail SWCC | فتح الملف |
79 | Repair oil leak at GSU transformer | KAFOU | KAFOU | 2021 | Completed | Repair oil leak at GSUtransformer at GT # 14 from flexible joint between transformer & radiator. | فتح الملف |
80 | Testing of Surge Arrestors at Jubail | THABEER CONTRACTING EST | THABEER CONTRACTING EST | 2022 | Completed | Testing of Surge Arrestors at Jubail | فتح الملف |
81 | Inspection & Testing of Circuit Breakers and Protection Relay of Electrical Switch Gear at Saudi Cement Sea Port | SAUDI CEMENT | SAUDI CEMENT | 2022 | Completed | Inspection & Testing of Circuit Breakers and Protection Relay of Electrical Switch Gear at Saudi Cement Sea Port | فتح الملف |
82 | Maintenance of Transformers | SAUDI CEMENT | SAUDI CEMENT | 2022 | Completed | Maintenance of Transformers | فتح الملف |
83 | Services for line # 6 RAW MILL elec. S/S Siemens MV Vacum CB & Protection Relays servicing & testing | SAUDI CEMENT | SAUDI CEMENT | 2022 | Completed | Services for line # 6 RAW MILL elec. S/S Siemens MV Vacum CB & Protection Relays servicing & testing | فتح الملف |
84 | JAL International Co. Ltd-DFRA Test of Transformer | JAL International | JAL International | 2022 | Completed | JAL International Co. Ltd-DFRA Test of Transformer | فتح الملف |
85 | Saudi Cement -REPLACEMENT OF CEMENT MILL 9&10 AND GYPSUM MV PANEL PROTECTION RELAYS | SAUDI CEMENT | SAUDI CEMENT | 2022 | Completed | Saudi Cement -REPLACEMENT OF CEMENT MILL 9&10 AND GYPSUM MV PANEL PROTECTION RELAYS | فتح الملف |
86 | ANNUAL CALIBRATION OF SIX (6) MV & LV KWH ENERGY METERS | SAUDI CEMENT | SAUDI CEMENT | 2022 | Completed | ANNUAL CALIBRATION OF SIX (6) MV & LV KWH ENERGY METERS | فتح الملف |
87 | Al-Fanar Construction -HUGRS - INVESTIGATION FOR HARADH - HUGRS LINE-2 TRIP | Alfanar Construction Co. | Alfanar Construction Co. | 2022 | Completed | Al-Fanar Construction -HUGRS - INVESTIGATION FOR HARADH - HUGRS LINE-2 TRIP | فتح الملف |
88 | العمارية بالرياض P3 لزوم محطة (VFD) توريد وتركيب جهاز مغير سرعة مضخة | Saudi Irrigation Organization | Saudi Irrigation Organization | 2022 | Completed | العمارية بالرياض P3 لزوم محطة (VFD) توريد وتركيب جهاز مغير سرعة مضخة | فتح الملف |
89 | (13.8KV/400V – 1MVA) أعمال الإصلاح المطلوبة في محطة قطاع رقم 5 على المحول | Saudi Irrigation Organization | Saudi Irrigation Organization | 2022 | Completed | (13.8KV/400V – 1MVA) أعمال الإصلاح المطلوبة في محطة قطاع رقم 5 على المحول | فتح الملف |
90 | Faras PP - MV Cable Termination from TM to mobile station | KAFOU Technical Services | KAFOU Technical Services | 2022 | Completed | Faras PP - MV Cable Termination from TM to mobile station | فتح الملف |
91 | SERVICES FOR LAYOUT OF 3-CORE 13.8KV POWER CABLE FROM S07 MAIN SUBSTATION TO CCBC S27A SUBSTATION | SAUDI CEMENT | SAUDI CEMENT | 2022 | Completed | SERVICES FOR LAYOUT OF 3-CORE 13.8KV POWER CABLE FROM S07 MAIN SUBSTATION TO CCBC S27A SUBSTATION | فتح الملف |
92 | Check & repair breaker # B316 , WO # 2202632612 / Emergency at Faras PP | KAFOU Technical Services | KAFOU Technical Services | 2022 | Completed | Check & repair breaker # B316 , WO # 2202632612 / Emergency at Faras PP | فتح الملف |
93 | Servicing unit no 15 GCB at Faras PP | KAFOU Technical Services | KAFOU Technical Services | 2022 | Completed | Servicing unit no 15 GCB at Faras PP | فتح الملف |
94 | Oil Filtration for 6 Transformers at AL JOUF PP | JAL International | JAL International | 2022 | Completed | Oil Filtration for 6 Transformers at AL JOUF PP | فتح الملف |
95 | Ghazlan PP - Inspection & Testing for Spare transformer (440/492.88 MVA) - Stage#2 | KAFOU Technical Services | KAFOU Technical Services | 2022 | Completed | Ghazlan PP - Inspection & Testing for Spare transformer (440/492.88 MVA) - Stage#2 | فتح الملف |
96 | STEP UP TRANSFORMER OIL LEAK ARRESTING & FILTRATION WORKS AT JUAIMA'H | Tihama Power Generation Company Ltd. | Tihama Power Generation Company Ltd. | 2022 | Completed | STEP UP TRANSFORMER OIL LEAK ARRESTING & FILTRATION WORKS AT JUAIMA'H | فتح الملف |
97 | THE SERVICING & TESTING OF 74 PROTECTION RELAYS | SAUDI CEMENT | SAUDI CEMENT | 2022 | Completed | THE SERVICING & TESTING OF 74 PROTECTION RELAYS | فتح الملف |
98 | Calibration of 32 Nos Energy Meters at SEC Al Jouf Power Plant. | KAFOU Technical Services | KAFOU Technical Services | 2022 | Completed | Calibration of 32 Nos Energy Meters at SEC Al Jouf Power Plant. | فتح الملف |
99 | Perform minor PM for eight (8) Nos Transformers at Faras Power Plant | KAFOU Technical Services | KAFOU Technical Services | 2022 | Completed | Perform minor PM for eight (8) Nos Transformers at Faras Power Plant | فتح الملف |
100 | Termination of MV cable ( 1X120mm2) | JTC | JTC | 2022 | Completed | Termination of MV cable ( 1X120mm2) | فتح الملف |
101 | Ghazlan PP - Inspection & Testing for Spare transformer (440/492.88 MVA) - Stage#1 | KAFOU Technical Services | KAFOU Technical Services | 2022 | Completed | Ghazlan PP - Inspection & Testing for Spare transformer (440/492.88 MVA) - Stage#1 | فتح الملف |
102 | Calibration of 30 NEXUS – 1250 Energy Meters at QCCPP 2022 | KAFOU Technical Services | KAFOU Technical Services | 2022 | Completed | Calibration of 30 NEXUS – 1250 Energy Meters at QCCPP 2022 | فتح الملف |
103 | Maintenance of Transformers at Al-Jouf Power Plant | KAFOU Technical Services | KAFOU Technical Services | 2022 | Completed | Maintenance of Transformers at Al-Jouf Power Plant | فتح الملف |
104 | Oil leak arresting works for 94 MVA, 70.7/13.8 kV Step Up Transformer at RTR (RFQ no. RTR4581) | Tihama Power Generation Company Ltd. | Tihama Power Generation Company Ltd. | 2022 | Completed | Oil leak arresting works for 94 MVA, 70.7/13.8 kV Step Up Transformer at RTR (RFQ no. RTR4581) | فتح الملف |
105 | Saudi Cement - Cement Ship Loader Diesel Engine | SAUDI CEMENT | SAUDI CEMENT | 2022 | Completed | Saudi Cement - Cement Ship Loader Diesel Engine | فتح الملف |
106 | فحص وتوريد وتركيب القاطع الكهربائي لزوم محطة الضخ الرئيسية بالرياض منفوحة | Saudi Irrigation Organization | Saudi Irrigation Organization | 2022 | Completed | فحص وتوريد وتركيب القاطع الكهربائي لزوم محطة الضخ الرئيسية بالرياض منفوحة | فتح الملف |
107 | "Installation, Testing & Commissioning and Oil filtration of six (06) transformers at Al-khobar SWCC station. 236 MVA , 230KV (two transformers) 186 MVA , 33 KV (two transformers) 50 MVA , 33 KV (two transformers)" | El SEWEDY ELECTRIC Co. | El SEWEDY ELECTRIC Co. | 2022 | Completed | Off-loading, instalaltion of radiators, busingings, pipes, cable boxes, etc .. , and vacuming, oil filtration, testing. | فتح الملف |
108 | Repair and filtration of START up xfmr oil leak repair @ JGP (PO # 22218) | Tihama Power Generation Company Ltd. | Tihama Power Generation Company Ltd. | 2022 | Completed | 1-Isolate transformer and disconnect HV terminals. 2-Drain oil to appropriate level. 3-Isolate HV & LV connections. 4-Repair of oil leak by replacement of Gasket. 5-Toping up transformer’s oil level. (Using supplied oil of 5 drums only). 6-Oil filtration. 7-Perform BDV oil test. 8-Take oil samples for DGA test after oil filtration. 9- Submit technical report. 10- Replace the Buchholz relay if necessary. | فتح الملف |
109 | Maintenance of one (01) 230/69 KV, 180 MVA Transformer at Khobar BSP (SEC Station) | JAL International | JAL International | 2022 | Completed | Major ovehouling, repair oil leaks and filtration of one (01) 230/69 KV, 180 MVA Transformer at Khobar BSP (SEC Station) | فتح الملف |
110 | Connection of TM unit in FARAS PP | Saudi Electricity Company | Saudi Electricity Company | 2022 | Completed | Laydown 13.8KV cables and fiber optical cables to connect emegency TM unit to the switchgear. | فتح الملف |
111 | ONLINE PD TESTING & HEALTHINESS EVALUATION OF LINE #7&8 SUBSTATIONS INCOMER POWER CABLES | Saudi Cement | Saudi Cement | 2022 | Completed | ONLINE PD TESTING & HEALTHINESS EVALUATION OF LINE #7&8 SUBSTATIONS INCOMER POWER CABLES | فتح الملف |
112 | SCC - SERVICING AND TESTING OF AUXILLARY TRANSFORMER LV BREAKER AND PROTECTION RELAY OF GT#6 AT POWER PLANT | Saudi Cement | Saudi Cement | 2022 | Completed | SERVICING AND TESTING OF AUXILLARY TRANSFORMER LV BREAKER AND PROTECTION RELAY OF GT#6 AT POWER PLANT | فتح الملف |
113 | SCC - replacement and service of 8 relays | Saudi Cement | Saudi Cement | 2022 | Completed | Replacement and T & C 8 Siemens Relay for 13.8 SWG | فتح الملف |
114 | SERVICES FOR INSTALLATION OF NEW CABLE TRAYS & LAYOUT/ TERMINATION OF SINGLE CORE 300KV (PRJ-23-012) | SAUDI CEMENT | SAUDI CEMENT | 2023 | In-Progress | SERVICES FOR INSTALLATION OF NEW CABLE TRAYS & LAYOUT/ TERMINATION OF SINGLE CORE 300KV (PRJ-23-012) | فتح الملف |
115 | Repair of Water Treatment Plant Transformer (AP7-1T1) | SAUDI CEMENT | SAUDI CEMENT | 2023 | Completed | Repair of Water Treatment Plant Transformer (AP7-1T1) | فتح الملف |
116 | Calibration of 23 Nos Energy Meters at SEC Qurayyah | KAFOU Technical Services | KAFOU Technical Services | 2023 | Completed | I. SCOPE OF WORK 1. 1. Our scope of work is limited to provide one (1) qualified expert plus required tools & test equipment to perform calibration of energy meters in QCCPP. | فتح الملف |
117 | Maintenance of Transformers at PP 12 Riyadh | KAFOU Technical Services | KAFOU Technical Services | 2023 | Completed | I. SCOPE OF WORK 1. Visual inspection, marking leaking points. 2. Drain transformer oil, leak repair. 3. Gasket replacement for leaking points. 4. Replacement of oil gauge where ever required. 5. Vacuuming, oil filling, filtration. 6. Provide a mobile crane. 7. Supply Senior testing engineer, electrical transformer specialist, OLTC specialist. 8. Supply of oil filtration plant, vacuum machine, and oil tankers. 9. Replace any defective mechanical protection device. 10. Take an oil sample for oil quality and DGA after the filtration is finished. 11. Electrical testing and mechanical checks are as follows: • Winding resistance measurement. • short circuit Impedance measurement. • Turns Ration Test. • Capacitance and tan delta for winding and HV bushing. • Excitation current. • HV winding dynamic resistance. • Insulation resistance. • Oil Temperature Indicator-calibration & testing. • Winding Temperature Indicator calibration & testing. • Transformer CT testing. • BDV, Buchholz relay, OMG, WTI and OTI. 12. OLTC maintenance and testing: for all transformers. • Static resistance measurement. • Motor current measurement. • Greasing of mechanical and electrical parts. • Dissolved gas analysis (DGA). • OLTC motor drive insulation resistance measurements and check mechanical bearings. | فتح الملف |
118 | SUPPLY & INSTALLATION OF NEUTRAL BUSHING AT ZONE 5 IN SAUDI IRRIGATION FACILITY | Saudi Irrigation Organization | Saudi Irrigation Organization | 2023 | Completed | SUPPLY & INSTALLATION OF NEUTRAL BUSHING AT ZONE 5 IN SAUDI IRRIGATION FACILITY | فتح الملف |
119 | SUPPLY & INSTALLATION OF PHASE # A BUSHING AT ZONE 5 IN SAUDI IRRIGATION FACILITY | Saudi Irrigation Organization | Saudi Irrigation Organization | 2023 | Completed | SUPPLY & INSTALLATION OF PHASE # A BUSHING AT ZONE 5 IN SAUDI IRRIGATION FACILITY | فتح الملف |
120 | SERVICES FOR ANNUAL CALIBRATION OF MV & LV KWH ENERGY METERS AT POWER PLANT (PR#17470) | SAUDI CEMENT | SAUDI CEMENT | 2023 | Completed | SERVICES FOR ANNUAL CALIBRATION OF MV & LV KWH ENERGY METERS AT POWER PLANT (PR#17470) | فتح الملف |
121 | MINOR PREVENTIVE MAINTENANCE OF 04EA. TRANSFORMERS FOR BFT#1 & 2 AND BOP#1 & 2 AT FARAS POWER PLANT | KAFOU Technical Services | KAFOU Technical Services | 2023 | Completed | MINOR PREVENTIVE MAINTENANCE OF 04EA. TRANSFORMERS FOR BFT#1 & 2 AND BOP#1 & 2 AT FARAS POWER PLANT | فتح الملف |
122 | JGP-GT3 UAT Transformer OLTC chamber flange oil leak urgent temporary rectification | Tihama Power Generation Company Ltd. | Tihama Power Generation Company Ltd. | 2023 | Completed | JGP-GT3 UAT Transformer OLTC chamber flange oil leak urgent temporary rectification | فتح الملف |
123 | Auxiliary transformers (17 nos.) Oil Leak at PP12 Power Plant | KAFOU Technical Services | KAFOU Technical Services | 2023 | Completed | Auxiliary transformers (17 nos.) Oil Leak at PP12 Power Plant | فتح الملف |
124 | Study, review, and implementation of relay settings (MV and LV system) for the faculty of pharmacy project, Hail University. | AL Fahd Company | AL Fahd Company | 2023 | Completed | Study, review, and implementation of relay settings (MV and LV system) for the faculty of pharmacy project, Hail University. | فتح الملف |
125 | Troubleshooting & Electrical Tests of T603 at Shedgum PP | KAFOU Technical Services | KAFOU Technical Services | 2023 | Completed | Troubleshooting & Electrical Tests of T603 at Shedgum PP | فتح الملف |
126 | SUPPLY PANEL,TPN DISTRIBUTION BOARD,6-WAYS, 250A, 400VAC, 60HZ, INCOMER:250A TP | SAUDI CEMENT | SAUDI CEMENT | 2023 | Completed | SUPPLY PANEL,TPN DISTRIBUTION BOARD,6-WAYS, 250A, 400VAC, 60HZ, INCOMER:250A TP | فتح الملف |
127 | SERVICES FOR INSTALLATION OF NEW CABLE TRAYS & LAYOUT/ TERMINATION OF SINGLE CORE 300KV (PRJ-23-011) | SAUDI CEMENT | SAUDI CEMENT | 2023 | Completed | SERVICES FOR INSTALLATION OF NEW CABLE TRAYS & LAYOUT/ TERMINATION OF SINGLE CORE 300KV (PRJ-23-011) | فتح الملف |
128 | SERVICES FOR INSTALLATION OF NEW CABLE TRAYS & LAYOUT/ TERMINATION OF SINGLE CORE 300KV | SAUDI CEMENT | SAUDI CEMENT | 2023 | Completed | SERVICES FOR INSTALLATION OF NEW CABLE TRAYS & LAYOUT/ TERMINATION OF SINGLE CORE 300KV | فتح الملف |
129 | ANNUAL OIL ANALYSIS FOR THE TRANSFORMER | SAUDI CEMENT | SAUDI CEMENT | 2023 | Completed | ANNUAL OIL ANALYSIS FOR THE TRANSFORMER | فتح الملف |
130 | Corrective maintenance and OLTC maintenance for no of three transformers (380KV,100MVA) at PP12 Durma Riyadh | KAFOU Technical Services | KAFOU Technical Services | 2023 | Completed | Corrective maintenance and OLTC maintenance for no of three transformers (380KV,100MVA) at PP12 Durma Riyadh | فتح الملف |
131 | SUPPLY PANEL,TPN DISTRIBUTION BOARD, 6WAYS, 250A, 400VAC, 60HZ, INCOMER:250A TP | SAUDI CEMENT | SAUDI CEMENT | 2023 | Completed | SUPPLY PANEL,TPN DISTRIBUTION BOARD, 6WAYS, 250A, 400VAC, 60HZ, INCOMER:250A TP | فتح الملف |
132 | Installation, testing & Commissioning of 2Ea. LV MCC with cable laying & connections at Qassim PP | KAFOU Technical Services | KAFOU Technical Services | 2023 | Completed | 1. Dismantling of Old MCC # 106 & 107. 2. Installation, Testing & Commissioning of New MCC (106 & 107) 3. Cable Laying and Termination (3.5C x 300sqmm), 2 Runs X 200 Meters, Termination 3 Core X 4 Ends. 4. Installation of Cable Tray- 400 x 100 x 1.5mm x 25 Meters (Height: 4Meters) 5. Laying of 4" PVC Pipe X 400 Meters for Underground cable. 6. Testing & Commissioning of 106 MCC with 1 Incoming Feeder + 6 Outgoing Feeder. 7. Testing & Commissioning of 107 MCC with 1 Incoming Feeder + 10 Outgoing Feeder. | فتح الملف |
133 | Troubleshooting & Electrical Tests of T603 at Shedgum PP | KAFOU Technical Services | KAFOU Technical Services | 2023 | Completed | Troubleshooting & Electrical Tests of T603 at Shedgum PP | فتح الملف |
134 | Faras PP ACM work on 4ea. Transformers (BFT & BOP# 1 & 2). | KAFOU Technical Services | KAFOU Technical Services | 2023 | Completed | Perform the corrective maintenance as above mentioned SOW for Tr BOP- 1: 1- Rectifying Oil leak from Buchholz relay flange. 2- Oil drain and gasket replacement required. 3- Tan-δ test. Perform the corrective maintenance as above mentioned SOW for Tr BOP- 2: 1- Rectifying Oil leak from Buchholz relay flange. 2- Rectifying Oil leak from the LV bushing and a Minor leak from the HV bushing. 3- Oil drain and gasket replacement required. 4- Rectifying N CT cracked in LV compartment & CT testing. Perform the corrective maintenance as above mentioned SOW for Tr BFT-1: 1- Rectifying Oil leak from Buchholz relay flange. 2- Rectifying Oil leak from the LV bushing and a Minor leak from the HV bushing. 3- Oil drain and gasket replacement required. 4- Tan-δ test. Perform the corrective maintenance as above mentioned SOW for Tr BFT-2: 1- Rectifying Oil leak from Buchholz relay flange. 2- Rectifying Oil leak from the LV bushing and a Minor leak from the HV bushing. 3- Oil drain and gasket replacement required. 4- Tan-δ test. | فتح الملف |
135 | Testing & Commissioning for MLT-6,7,8,9 and SD-6,7,8 for ATCO-ARAR Project-LV penels | ATCO | ATCO | 2023 | Completed | Testing & Commissioning for MLT-6,7,8,9 and SD-6,7,8 for ATCO-ARAR Project-LV penels | فتح الملف |
136 | SERVICES FOR THE SUPPLY OF MATERIALS, INSTALLATION AT SITE & COMMISSIONING FOR THE MV PANELS PROTECTION RELAYS FOR LINE #6 | SAUDI CEMENT | SAUDI CEMENT | 2023 | Completed | SERVICES FOR THE SUPPLY OF MATERIALS, INSTALLATION AT SITE & COMMISSIONING FOR THE MV PANELS PROTECTION RELAYS FOR LINE #6 | فتح الملف |
137 | Overhaul and repair ARAMCO Transformers-3Nos in GCC Lab | GCC ELECTRICAL TESTING LABORATORY | GCC ELECTRICAL TESTING LABORATORY | 2023 | Completed | Overhaul and repair ARAMCO Transformers-3Nos in GCC Lab | فتح الملف |
138 | EXIT-10 AL HAMRA DEVELOPMENT PROJECT, RIYADH | AL FUTTAIM ENGINEERING & TECHNOLOGIES | AL FUTTAIM ENGINEERING & TECHNOLOGIES | 2023 | In-progress | EXIT-10 AL HAMRA DEVELOPMENT PROJECT, RIYADH | فتح الملف |
139 | Repairing & Testing of GT-6 Generator Breaker Switchgear Panel (K-12). | SAUDI CEMENT | SAUDI CEMENT | 2023 | Completed | Repairing & Testing of GT-6 Generator Breaker Switchgear Panel (K-12). | فتح الملف |
140 | SERVICING OF 110VDC BATTERY CHARGER FOR LINE #6 RAW MILLS, KILN COOLER, CEMENT MILLS #9 &10, AND GYPSUM AREAS. | SAUDI CEMENT | SAUDI CEMENT | 2023 | SERVICING OF 110VDC BATTERY CHARGER FOR LINE #6 RAW MILLS, KILN COOLER, CEMENT MILLS #9 &10, AND GYPSUM AREAS. | فتح الملف | |
141 | T.M Unit Cable Termination & Jointing at Faras PP | KAFOU Technical Services | KAFOU Technical Services | 2023 | Completed | T.M Unit Cable Termination & Jointing at Faras PP | فتح الملف |
142 | SHED PP - INVESTIGATION FOR Unit 13 CB TRIP. | KAFOU Technical Services | KAFOU Technical Services | 2023 | Completed | SHED PP - INVESTIGATION FOR Unit 13 CB TRIP. | فتح الملف |
143 | SEC-Jazan Power Plant- (13.8KV BSDG SWGR) Installation, Testing & Commissioning | KAFOU Technical Services | KAFOU Technical Services | 2023 | Completed | SEC-Jazan Power Plant- (13.8KV BSDG SWGR) Installation, Testing & Commissioning | فتح الملف |
144 | Installing works & extra T&C works for Al Hassa housing SS 115/13.8KV | Almashariq Trading and Contracting Company | Almashariq Trading and Contracting Company | 2023 | In-Progress | 1- Installation of: 1.1 Installation of 3 -13.8kV Capacitor Bank with related series reactor, capacitor, CT, VT & Surge Arrestors. 1.2 Installation of Battery system. 1.3 Installation of Communication panels at Comm. Room. 1.4 Installation of SUB-DCDB panel. 1.5 Installation of Outdoor Lighting Panels and indoor lighting system (Remaining panels) 1.6 Installation Lightening protection system and all grounding installations rather than ground mesh. 1.7 "Installation & Connection of ground mesh as per approved drawing." 1.8 "Installation SAS Disc & related HID. 1.9 "Install and Erection of protection Panels Related Alhassa Housing CKT1 &CKT2 With AMI Panel” (Remote End SS) 1.10 "Installation of Communication panels at Comm. Room" 1.11 Installation for Telephone system panels. 2- MV Cable Laying and pulling: 2.1 "Power Transformer :6R-1C*630SQ.MM,15kV, CU/XLPE CABLE/PHASE (TYP" 2.2 "Aux. Transformer:1R*3C*300SQ.MM XLPE.CU CONDUCTOR 15KV CABLES" 2.3 "Capacitor’s Bank: 1R*1C*630 SQ.MM 15KV CU/XLPE CABLES/PHASE" 3- MV Power Cable Termination. 4- Laying and Puling LV Control Cable 5- LV Control Cable Termination: 6- Oil Circulation / Filtration for 3 Power Transformer 132/13.8 KV 80 MVR | فتح الملف |
145 | Preventive maintenance and testing of 14 GCBs in PP12 | KAFOU Technical Services | KAFOU Technical Services | 2023 | Completed | Preventive maintenance and testing of 14 GCBs in PP12 | فتح الملف |
146 | THE ASSESSMENT & TESTING OF PLANTWIDE LINE #7&8 LOW VOLTAGE CAPACITOR BANKS & CONTROLS | SAUDI CEMENT | SAUDI CEMENT | 2023 | Completed | THE ASSESSMENT & TESTING OF PLANTWIDE LINE #7&8 LOW VOLTAGE CAPACITOR BANKS & CONTROLS | فتح الملف |
147 | SERVICES FOR 13.8KV/ 400V 60HZ POWER SUPPLY ARRANGEMENT FOR HOFUF KHD & GUEST HOUSING | SAUDI CEMENT | SAUDI CEMENT | 2023 | Completed | SERVICES FOR 13.8KV/ 400V 60HZ POWER SUPPLY ARRANGEMENT FOR HOFUF KHD & GUEST HOUSING | فتح الملف |
148 | Urgent Repairing & Testing of GT-6 Generator Breaker Switchgear Panel (K-12). | SAUDI CEMENT | SAUDI CEMENT | 2023 | Completed | Urgent Repairing & Testing of GT-6 Generator Breaker Switchgear Panel (K-12). | فتح الملف |
149 | SERVICING OF 110VDC BATTERY CHARGER FOR LINE #6 RAW MILLS, KILN COOLER, CEMENT MILLS #9 &10, AND GYPSUM AREAS. | SAUDI CEMENT | SAUDI CEMENT | 2023 | Completed | SERVICING OF 110VDC BATTERY CHARGER FOR LINE #6 RAW MILLS, KILN COOLER, CEMENT MILLS #9 &10, AND GYPSUM AREAS. | فتح الملف |
150 | Jeddah Warehouse – survey, site visit and Transformer’s oil sampling. | NRTC | NRTC | 2023 | Completed | Jeddah Warehouse – survey, site visit and Transformer’s oil sampling. | فتح الملف |
151 | SERVICES FOR SUPPLY, INSTALLATION AND COMMISSIONING OF BUS COUPLER SWITCH FOR THE T2 PACKING PLANT LOW VOLTAGE SECONDRY LINE (PR# 27078) | SAUDI CEMENT | SAUDI CEMENT | 2023 | In-Progress | SERVICES FOR SUPPLY, INSTALLATION AND COMMISSIONING OF BUS COUPLER SWITCH FOR THE T2 PACKING PLANT LOW VOLTAGE SECONDRY LINE (PR# 27078) | فتح الملف |
152 | Upgradation and replacement of defective protection relay | SAUDI CEMENT | SAUDI CEMENT | 2023 | In-Progress | Upgradation and replacement of defective protection relay | فتح الملف |
153 | Riyadh PP12 GT&ST-GSUTs (470MVA&454MVA) HV Cable Box - Oil drain and filtration work | KAFOU Technical Services | KAFOU Technical Services | 2023 | Completed | Riyadh PP12 GT&ST-GSUTs (470MVA&454MVA) HV Cable Box - Oil drain and filtration work | فتح الملف |
تحميل...